ISA Energía (formerly ISA Transelca) installed 21 SmartValves across five 220 kV circuits in Colombia’s Atlántico region. The project increased usable capacity by approximately 300 MW to support firm connection of new generation.
Studies forecast overloads on several 220 kV circuits, particularly under N-1 contingencies, as approved wind and solar generation connected to the Atlántico network. Around 1.5 GW of wind and solar generation had already been approved for connection.
After reviewing network options, Colombia’s national planning agency UPME selected ISA Energía’s SmartValve proposal. The devices dynamically rebalance power flows from overloaded lines onto paths with spare capacity across multiple substations.
The 2024 deployment installed 21 SmartValves across five 220 kV circuits, including an indoor installation, providing 210 MVAr of controllable capability. The distributed configuration makes effective use of substation space and can be adapted as requirements change.
The Atlántico project helps manage expected overloads across critical transmission circuits as new generation connects to the system.
Relieved congestion on 220 kV circuits to support firm connection of new generation.
Distributed across five circuits with 21 devices, including an indoor deployment.
Dynamic power flow control supports reliable service under N-1 conditions.
Installation in existing substations avoided extended corridor construction and lengthy permitting.
Read the full case study for the network constraints, distributed layout and capacity delivered.
See how grid-enhancing technologies are being deployed across different systems and regions.
Fill out the form below to access the Atlántico project case study.