PG&E San Jose Area Project
Case study

PG&E San Jose Area Project

Facing more than 1.4 GW of data center projects in final engineering, CAISO, PG&E, and Silicon Valley Power needed a faster solution to maintain reliability. SmartValve was selected to create near-term headroom while longer-term upgrades are planned.

View project overview
PG&E San Jose Area SmartValve deployment
100 MW Immediate transfer capability relief
510 MW Potential firm load support
34% Thermal overload reduction

Relieving a limiting 115 kV facility to serve growing data center demand

More than 1.4 GW of data center projects were in final engineering for the San Jose area, while major transmission upgrades were not expected in the near term.

CAISO, PG&E, and Silicon Valley Power needed a solution that could be deployed faster than reconductoring or energy storage, maintain NERC reliability criteria, and create firm load headroom using existing infrastructure.

After evaluating alternatives, SmartValve was selected as the most effective and timely option. By redirecting power from a limiting 115 kV facility to underutilised parallel lines, SmartValve provides about 100 MW of immediate transfer capability relief and can support up to 510 MW of firm load, depending on load location, while meeting NERC reliability criteria.

The solution fits within the existing substation footprint, requires no new corridor work or permitting, and is designed for rapid deployment, future expansion, or relocation as system needs evolve. Deployment is estimated at approximately 18 months.

Addressing 1.4 GW of data center demand

Creates headroom for data centers already in operation while enabling new connections currently in final engineering.

No new footprint required

SmartValve fits within the existing substation footprint, avoiding corridor work, permitting, and construction disruption.

Fast, flexible capacity for a grid under pressure

The PG&E San Jose Area Project shows how Advanced Power Flow Control can address critical load growth in time-constrained situations, without the cost or lead times of conventional transmission upgrades.

Maintains NERC reliability criteria

Manages thermal overloads on the limiting 115 kV facility while longer-term transmission upgrades are planned.

Supports data center load growth

Creates headroom for data centers already in operation while enabling new connections currently in final engineering.

Fits the existing substation footprint

No new corridor work or permitting required, avoiding construction disruption and accelerating deployment.

Redeployable as system needs evolve

Designed for future expansion or relocation, eliminating the risk of stranded assets when longer-term upgrades arrive.

SmartValve deployment on the 115 kV network

A look at the Advanced Power Flow Control deployment serving the San Jose area transmission network.

PG&E San Jose Area Project: creating headroom for data center load

Access the full case study to learn how SmartValve provided 100 MW of immediate transfer capability relief, supports up to 510 MW of firm load, and reduced thermal overloads by up to 34% on the limiting 115 kV facility.

PG&E San Jose Area case study preview